Biomass Boiler Magnon, Huelva (ES)

Overview Boiler Data Boiler Design: vertical with two-drums-vertical evaporator and vertical economizerSteam Flow: 105 t/h @ 68 bar/ 485°CDimensions: 18.9 m H x 4.5 m W x 10.7m L (excl. economizer in a separate section)Fuel / Boiler Type: Biomass/Fluidized bedSPG in Operation since: 1 EG10XL from November 2019, upstream of… Read More

Copper Smelter Aurubis (BG)

Overview Boiler Data Boiler Design: Horizontal (twin type design)Steam Flow: 65 t/h @ 48 bar saturated steam Dimensions: 12 m H x 6 m W x 45 m total length Fuel / Boiler Type: Waste heat boiler installed after flash copper smelter furnace SPG in Operation since: 4 EG10L from 2016,… Read More

Uerdingen Currenta GmbH & Co

Overview Boiler Data Benson type 3-pass boiler, melting chamber Steam Flow: 175 t/h @ 530°C / bar Boiler Width: 7 m Fuel: Black Coal / Industrial Power Plant SPG in Operation since: 2017 / 2018, 2 x EG10 Shock Pulse Interval: 1 SP/h Improvement of the Cleaning Cycle The boiler… Read More

MSWI KEZO Hinwil

Overview 24 t/h steam capacity per boiler3rd pass: W 5 x L 1.8 m x H 10 mbundles: Pitch H/V/tube Da x t; bundle height PSH2: 130 / av. 80 / 38 x 5 mm; ca. 0.9 m FSH1: 140 / av. 80 / 38 x 5 mm; 0.9 m… Read More

MSW Boiler Lucerne (Perlen)

Overview 2 boilers with 58 t/h steam flow per unit, since 2015.Capacity increase to 70 t/h in 2020 (120% of the original design)Boiler width 5.5 m6x Shock Pulse Generator EG10L, since 01/2015 (3 per boiler), enable to maintain a constant RG temperature at the inlet to the horizontal pass, even… Read More

MSW Boiler Line 4, Zuchwil

Overview 32 t/h steam production at 38 bar, 375°C; boiler width horizontal pass 3’120mm1x Shock Pulse Generator EG10XL, since 30.03.2015Boiler operation period fixed at 4 month (4 lines which run in parallel); before SPG installation reduce boiler load to keep the outlet temperature in a permissible range; afterwards boiler load… Read More

MSW Boiler Zurich

Overview 52 t/h steam flow, 40 bar, 420°CBoiler width 7.2 mThe 3rd pass contains a separation wall in the middle of the pass1 x Shock Pulse Generator TwinL, since 30.11.2015; at 2nd passGood cleaning effect at 2nd an 3rd pass, significantly lower flue gas temperature at inlet to horizontal pass;… Read More

EfW plant Kotka

Overview Energy from Waste Plant, incinerating municipal solid waste4-pass horizontal boiler39 t/h steam capacity2nd pass: W 4.9 x L 2.7 x H 13m 3rd pass: W 4.9 x L 3.3 x H 13m2 x Shock Pulse Generators EG10 (SPG), installed since 01/2010, located in 2nd + 3rd passSince installation of… Read More

Industrial Boiler Aomori

Overview Energy from Waste Plant, incinerating 120’000 t/y shredding residues, sewage sludge and medical wasteShredding residues originate from recycling of cars, trains, industrial wastes, household appliances, etcThe plant consists of a fluidized bed gasifier, an ash melting furnace and a boilerMetals (Fe, Al, Cu), vitrified glass and fly ash are… Read More

MSW Boiler NL-Twence

Overview 62 t/h steam flow, 43 bar, 414°C4-pass horizontal boiler; width empty pass: 7.6m; width convection pass: 6.0mbundles: Pitch T/L/tube Diameter; bundle height EVAP1: 120 / 120 / 44.5; 6.3m SH3: 120 / 120 / 44.5; 6.3m SH2: 120 / 120 / 44.5; 6.3m SH1: 120 / 120 / 44.5;… Read More

×