EfW plant Kotka
Finland
Overview
Energy from Waste Plant, incinerating municipal solid waste
4-pass horizontal boiler
39 t/h steam capacity
2nd pass: W 4.9 x L 2.7 x H 13m 3rd pass: W 4.9 x L 3.3 x H 13m
2 x Shock Pulse Generators EG10 (SPG), installed since 01/2010, located in 2nd + 3rd pass
Since installation of the SPG’s: Temperature at entrance to 4th pass remains below 640°C, SH3 does not clogg any more
The plant can achieve the desired continuous operating period
The SPG’s replace water canons
before installation of the SPG’s, additional manual explosion cleaning was applied twice a year
Plant supplier: Keppel Seghers
Plant operator: Kotka Energia Oy
Stoker
1st pass : W 4.9 m; radiation pass
2nd pass: W 4.9 x L 2.7 x H 13m; radiation pass
3rd pass: W 4.9 x L 3.3 x H 13 m; radiation pass
4th pass: W 3.9 x L 22.5 x H 6.0 m convective pass
Bundle arrangement in 4th pass: EVAP1: 3 rows SH3 : 18 rows SH2 : 18 rows SH1 : 18 rows EVAP2: 18 rows Eco: 3 bundles
Shock Pulse Generator 2
nd
pass:
2-3 hours
Shock Pulse Generator 3
rd
pass:
1 hour
Impressions of the reference plant
×